A38 Traffic Management Bulletin w/c 20 January 2025

Archives

A38 Traffic Management Bulletin w/c 20 January 2025

Published 17 January 2025

A38 E-Bulletin wc 20JAN2025

Hello and welcome to our weekly A38 Traffic Management Bulletin.

A38 Toyota Island to Little Eaton LED lighting work

We’re returning to complete the LED lighting upgrade work that we started last Autumn along the A38, between Toyota Island and Little Eaton. The new LED lighting will be more energy efficient and require less maintenance in the future.
Our work will start on 20 January and finish in April. This will be carried out on weeknights, between 8pm and 6am, predominantly under slip road and lane closures, with some full carriageway closures along this stretch.

The closures for this scheme for the following 2 weeks are:

  • 20 January – Toyota Island southbound exit slip road closure
  • 21 January – Toyota Island northbound entry slip road closure
  • 22 January – Findern Interchange northbound exit slip road closure
  • 23 January – Findern Interchange southbound entry slip road closure
  • 24 January to 31 January – Toyota Island to Findern Interchange full northbound carriageway closure

Third Party Work
Please be aware that Staffordshire County Council have some roadworks projects around the A38 in Burton. For further information on these roadworks, please use the following link – https://www.staffordshire.gov.uk/Highways/roadworks/eaststaffs/Overview.aspx

We’re always looking to improve the way we work. If you haven’t provided your feedback then we would like to ask you to complete a short questionnaire. If you could spare just 4 minutes (maximum) and complete the survey, click here.

Wishing you all a safe journey