A38 roadworks delayed

Archives

A38 roadworks delayed

Published 3 August 2018

I just wanted to make you all aware that we have had to defer the upcoming work on the A38 signs. Our previous start date of Monday, 6 August has now moved. We’re currently looking at starting this work Monday, 20 August 2018.
Start of works: Monday, 20 August 2018*
End of works: Friday, 22 September 2018*
Hours of work: 9pm to 6am Monday to Friday
*Please note that all our planned roadworks are subject to change due to weather conditions or unforeseen circumstances.
Detail of works
We’ll be replacing signs that have reached the end of their serviceable life. The new signs will comply with current standards and will improve visibility of the signs, especially at night and in poor weather conditions. Those sign that require illumination will also have new LED lighting units installed, which use less electricity. Replacing the signs will improve this section of the A38 with clearer signing, which will be easier to read.
Traffic restrictions
Work will be done in 3 phases. We’ll be working mainly using lane closures. However road closures will be required on either the northbound or southbound carriageway. The map below shows the 3 diversions that will be in place, as agreed with Staffordshire County Council.
Phase 1
A38 northbound and southbound from Swinfen roundabout to Wood End Lane. This will require 1 northbound road closure and 2 southbound road closures as well as lane closures.
Phase 2
A38 northbound and southbound between Wood End Lane and Alrewas junction. This will require 2 northbound road closures and 1 southbound road closure as well as lane closures.
Phase 3
A38 northbound and southbound between Alrewas junction and Toyota Island. This will require 2 northbound road closures and 2 southbound road closures as well as lane closures.